Quiz-summary
0 of 30 questions completed
Questions:
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
Information
Premium Practice Questions
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading...
You must sign in or sign up to start the quiz.
You have to finish following quiz, to start this quiz:
Results
0 of 30 questions answered correctly
Your time:
Time has elapsed
Categories
- Not categorized 0%
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- 10
- 11
- 12
- 13
- 14
- 15
- 16
- 17
- 18
- 19
- 20
- 21
- 22
- 23
- 24
- 25
- 26
- 27
- 28
- 29
- 30
- Answered
- Review
-
Question 1 of 30
1. Question
Consider a project where, midway through execution, a major competitor launches a disruptive product that fundamentally alters the market landscape. The project’s original objectives, while still valid in principle, are now challenged by this new reality, necessitating a re-evaluation of the project’s approach and potentially its scope. The Project Manager must lead the team through this period of uncertainty, ensuring continued progress and morale. Which PRINCE2 Practitioner behavioral competency is most critical for the Project Manager to demonstrate in this specific situation to ensure the project’s continued relevance and eventual success?
Correct
The scenario describes a project team facing a significant shift in strategic direction due to unforeseen market changes. The project manager, Anya, needs to guide the team through this transition. Anya’s ability to adjust project priorities, manage the inherent ambiguity, and maintain team effectiveness during this period is paramount. She must also be open to pivoting the project’s strategy, demonstrating adaptability and flexibility. This aligns directly with the PRINCE2 Practitioner competency of Adaptability and Flexibility, which emphasizes adjusting to changing priorities, handling ambiguity, maintaining effectiveness during transitions, pivoting strategies when needed, and openness to new methodologies. While other competencies like Communication Skills, Problem-Solving Abilities, and Leadership Potential are also relevant, the core challenge presented is the need to adapt the project’s approach in response to external pressures, making Adaptability and Flexibility the most encompassing and critical competency in this specific situation. Anya’s proactive communication about the changes and her efforts to resolve team concerns would fall under Communication Skills and Conflict Resolution respectively, but the fundamental requirement for success is her and the team’s ability to adapt.
Incorrect
The scenario describes a project team facing a significant shift in strategic direction due to unforeseen market changes. The project manager, Anya, needs to guide the team through this transition. Anya’s ability to adjust project priorities, manage the inherent ambiguity, and maintain team effectiveness during this period is paramount. She must also be open to pivoting the project’s strategy, demonstrating adaptability and flexibility. This aligns directly with the PRINCE2 Practitioner competency of Adaptability and Flexibility, which emphasizes adjusting to changing priorities, handling ambiguity, maintaining effectiveness during transitions, pivoting strategies when needed, and openness to new methodologies. While other competencies like Communication Skills, Problem-Solving Abilities, and Leadership Potential are also relevant, the core challenge presented is the need to adapt the project’s approach in response to external pressures, making Adaptability and Flexibility the most encompassing and critical competency in this specific situation. Anya’s proactive communication about the changes and her efforts to resolve team concerns would fall under Communication Skills and Conflict Resolution respectively, but the fundamental requirement for success is her and the team’s ability to adapt.
-
Question 2 of 30
2. Question
Anya, the Project Manager for a new CRM implementation, is in the ‘Initiating a Project’ process. The Project Board has just requested the addition of a complex integration with a legacy accounting system, a requirement not previously identified. Anya must determine the most effective PRINCE2-compliant method to address this significant scope change request.
Correct
The scenario describes a project manager, Anya, leading a project to implement a new customer relationship management (CRM) system. During the ‘Initiating a Project’ process, the project board has requested a significant alteration to the project’s scope, specifically adding a complex integration with a legacy accounting system. This integration was not initially considered and represents a substantial increase in complexity and risk. Anya needs to determine the most appropriate PRINCE2 response.
The PRINCE2 methodology emphasizes managing by exception and requires that any deviation from the agreed-upon Project Initiation Documentation (PID), particularly regarding scope, budget, or timeline, must be addressed through formal change control. The request for a new integration falls under this category.
Anya’s first step should be to assess the impact of this change. This involves understanding the effort required, the potential risks, the impact on the timeline and budget, and the overall feasibility. This assessment is typically documented in an Exception Report if the deviation exceeds agreed tolerances, or more commonly, a Change Request if it’s a proposed change that needs approval. Given the magnitude of the requested change (adding a complex integration), it’s highly likely to impact tolerances.
The Project Board is responsible for approving significant changes. Therefore, Anya must present the proposed change and its implications to the Project Board. The correct PRINCE2 approach is to prepare a detailed Change Request, outlining the proposed change, the reasons for it, the impact assessment (including cost, time, risk, and quality), and potential options for implementation. This document is then submitted to the Project Board for their decision.
If the change is approved, the PID will need to be updated to reflect the new scope and associated plans. If it’s rejected, the project continues as planned, or alternative solutions might be sought.
Therefore, the most appropriate action for Anya is to create a detailed Change Request to present to the Project Board for their decision on how to proceed with the requested integration. This aligns with the PRINCE2 principles of continued business justification, managing by stages, and managing by exception, as well as the ‘Controlling a Stage’ and ‘Managing Product Delivery’ processes where change control is fundamental.
Incorrect
The scenario describes a project manager, Anya, leading a project to implement a new customer relationship management (CRM) system. During the ‘Initiating a Project’ process, the project board has requested a significant alteration to the project’s scope, specifically adding a complex integration with a legacy accounting system. This integration was not initially considered and represents a substantial increase in complexity and risk. Anya needs to determine the most appropriate PRINCE2 response.
The PRINCE2 methodology emphasizes managing by exception and requires that any deviation from the agreed-upon Project Initiation Documentation (PID), particularly regarding scope, budget, or timeline, must be addressed through formal change control. The request for a new integration falls under this category.
Anya’s first step should be to assess the impact of this change. This involves understanding the effort required, the potential risks, the impact on the timeline and budget, and the overall feasibility. This assessment is typically documented in an Exception Report if the deviation exceeds agreed tolerances, or more commonly, a Change Request if it’s a proposed change that needs approval. Given the magnitude of the requested change (adding a complex integration), it’s highly likely to impact tolerances.
The Project Board is responsible for approving significant changes. Therefore, Anya must present the proposed change and its implications to the Project Board. The correct PRINCE2 approach is to prepare a detailed Change Request, outlining the proposed change, the reasons for it, the impact assessment (including cost, time, risk, and quality), and potential options for implementation. This document is then submitted to the Project Board for their decision.
If the change is approved, the PID will need to be updated to reflect the new scope and associated plans. If it’s rejected, the project continues as planned, or alternative solutions might be sought.
Therefore, the most appropriate action for Anya is to create a detailed Change Request to present to the Project Board for their decision on how to proceed with the requested integration. This aligns with the PRINCE2 principles of continued business justification, managing by stages, and managing by exception, as well as the ‘Controlling a Stage’ and ‘Managing Product Delivery’ processes where change control is fundamental.
-
Question 3 of 30
3. Question
During the execution of the ‘Orion’ project, a critical strategic shift within the client organization led to a significant re-evaluation of their core business objectives. This directly influenced the desired outcomes of the Orion project, necessitating a potential alteration of its scope and deliverables. The Project Manager, observing these evolving requirements and anticipating their impact on the current plan, considered the most appropriate PRINCE2 principle to guide their immediate response to ensure continued alignment with the client’s revised strategic direction. Which PRINCE2 principle would most effectively support the Project Manager in navigating this situation to facilitate a controlled adaptation of the project’s strategy?
Correct
The core of this question lies in understanding how PRINCE2 principles guide behaviour and decision-making, particularly in the face of evolving project circumstances. The scenario describes a project experiencing scope creep due to a key stakeholder’s changing business needs, which directly impacts the project’s initial plan and objectives. The Project Manager needs to adapt their approach to maintain control and ensure the project remains viable.
The PRINCE2 principle of “Manage by Stages” is crucial here. It dictates that a project is divided into manageable and controllable phases. At the end of each stage, the Project Board reviews progress, learns from experience, and decides whether to continue. This principle inherently supports adaptability and flexibility by providing natural review points where changes can be assessed and incorporated, or rejected.
The principle of “Focus on Products” emphasizes defining and delivering the project’s products. When stakeholder needs change, the product descriptions may need revision. This necessitates a controlled approach to change, which is managed through the “Manage by Exception” principle, where the Project Manager only escalates deviations from tolerances. However, the *decision* to adapt the strategy and potentially re-plan is best facilitated by the structured review points offered by “Manage by Stages.”
The principle of “Tailor to Suit the Project Environment” is also relevant, as the Project Manager must adapt the PRINCE2 processes to the specific context. However, it doesn’t prescribe *how* to adapt in this specific situation. “Continued Business Justification” is vital, as any changes must still align with the project’s business case.
Considering the scenario, the most effective way to handle the evolving stakeholder needs and potential scope creep, while adhering to PRINCE2 principles, is to leverage the structured review points of the “Manage by Stages” principle. This allows for a formal assessment of the impact of the changes on the project’s objectives, business case, and tolerances, leading to a decision on whether to approve revised plans or pivot the strategy. The Project Manager would typically prepare an Exception Report if tolerances are forecast to be exceeded, but the fundamental PRINCE2 mechanism for adapting strategy at a higher level, based on changing business needs, is through stage boundaries. Therefore, initiating a review at the next stage boundary to reassess the project’s direction and potentially re-plan is the most PRINCE2-aligned response.
Incorrect
The core of this question lies in understanding how PRINCE2 principles guide behaviour and decision-making, particularly in the face of evolving project circumstances. The scenario describes a project experiencing scope creep due to a key stakeholder’s changing business needs, which directly impacts the project’s initial plan and objectives. The Project Manager needs to adapt their approach to maintain control and ensure the project remains viable.
The PRINCE2 principle of “Manage by Stages” is crucial here. It dictates that a project is divided into manageable and controllable phases. At the end of each stage, the Project Board reviews progress, learns from experience, and decides whether to continue. This principle inherently supports adaptability and flexibility by providing natural review points where changes can be assessed and incorporated, or rejected.
The principle of “Focus on Products” emphasizes defining and delivering the project’s products. When stakeholder needs change, the product descriptions may need revision. This necessitates a controlled approach to change, which is managed through the “Manage by Exception” principle, where the Project Manager only escalates deviations from tolerances. However, the *decision* to adapt the strategy and potentially re-plan is best facilitated by the structured review points offered by “Manage by Stages.”
The principle of “Tailor to Suit the Project Environment” is also relevant, as the Project Manager must adapt the PRINCE2 processes to the specific context. However, it doesn’t prescribe *how* to adapt in this specific situation. “Continued Business Justification” is vital, as any changes must still align with the project’s business case.
Considering the scenario, the most effective way to handle the evolving stakeholder needs and potential scope creep, while adhering to PRINCE2 principles, is to leverage the structured review points of the “Manage by Stages” principle. This allows for a formal assessment of the impact of the changes on the project’s objectives, business case, and tolerances, leading to a decision on whether to approve revised plans or pivot the strategy. The Project Manager would typically prepare an Exception Report if tolerances are forecast to be exceeded, but the fundamental PRINCE2 mechanism for adapting strategy at a higher level, based on changing business needs, is through stage boundaries. Therefore, initiating a review at the next stage boundary to reassess the project’s direction and potentially re-plan is the most PRINCE2-aligned response.
-
Question 4 of 30
4. Question
A project to develop a new software application is in its execution phase, adhering strictly to the approved baseline. Midway through the current management stage, the project team discovers a significant, unforeseen market shift that presents a substantial opportunity for enhanced product functionality, which could dramatically increase market share. This new functionality, however, falls outside the currently defined scope and would require a considerable reallocation of resources and a revised timeline. The Project Manager has analyzed the potential benefits and risks, concluding that pursuing this opportunity is strategically vital. What is the most appropriate next step for the Project Manager to take in accordance with PRINCE2 principles and practices?
Correct
The scenario describes a project experiencing significant scope creep due to an emergent understanding of a critical market need that was not initially identified. The Project Manager’s initial response is to focus on maintaining the existing plan and managing the deviation through the established change control process. However, the rapid evolution of the market and the potential for significant competitive advantage necessitate a more proactive and adaptable approach.
In PRINCE2, the principle of “Manage by Exception” is crucial, but it is balanced by the need for “Continued Business Justification” and “Manage by Stages.” When a significant external factor, like a rapidly evolving market opportunity, emerges, the Project Manager must assess its impact on the project’s viability and objectives. Simply adhering to the existing change control process without re-evaluating the project’s strategic alignment and potential benefits might lead to the project becoming obsolete or failing to capitalize on a critical window of opportunity.
The Project Board is responsible for providing overall direction and is empowered to make strategic decisions. By escalating the situation to the Project Board with a clear analysis of the opportunity, the potential impact on the project’s objectives, and recommended options (including a revised approach that might involve a temporary suspension of work on certain elements to focus on the new opportunity, or a significant change request), the Project Manager enables the Board to make an informed decision. This aligns with the PRINCE2 principle of “Focus on Products” by ensuring that the project continues to deliver value, and “Manage by Stages” by allowing for re-planning at stage boundaries. The Project Manager’s role here is not just to control deviations but to facilitate strategic decision-making when the project’s context fundamentally shifts. Therefore, the most appropriate action is to present the situation and options to the Project Board for a strategic decision.
Incorrect
The scenario describes a project experiencing significant scope creep due to an emergent understanding of a critical market need that was not initially identified. The Project Manager’s initial response is to focus on maintaining the existing plan and managing the deviation through the established change control process. However, the rapid evolution of the market and the potential for significant competitive advantage necessitate a more proactive and adaptable approach.
In PRINCE2, the principle of “Manage by Exception” is crucial, but it is balanced by the need for “Continued Business Justification” and “Manage by Stages.” When a significant external factor, like a rapidly evolving market opportunity, emerges, the Project Manager must assess its impact on the project’s viability and objectives. Simply adhering to the existing change control process without re-evaluating the project’s strategic alignment and potential benefits might lead to the project becoming obsolete or failing to capitalize on a critical window of opportunity.
The Project Board is responsible for providing overall direction and is empowered to make strategic decisions. By escalating the situation to the Project Board with a clear analysis of the opportunity, the potential impact on the project’s objectives, and recommended options (including a revised approach that might involve a temporary suspension of work on certain elements to focus on the new opportunity, or a significant change request), the Project Manager enables the Board to make an informed decision. This aligns with the PRINCE2 principle of “Focus on Products” by ensuring that the project continues to deliver value, and “Manage by Stages” by allowing for re-planning at stage boundaries. The Project Manager’s role here is not just to control deviations but to facilitate strategic decision-making when the project’s context fundamentally shifts. Therefore, the most appropriate action is to present the situation and options to the Project Board for a strategic decision.
-
Question 5 of 30
5. Question
Consider a large-scale infrastructure project developing a new high-speed rail network. Midway through the execution phase, an unexpected government directive mandates significantly stricter environmental impact assessment regulations for all major construction projects. This new regulation introduces new documentation requirements, reporting frequencies, and potential construction methodology limitations, directly impacting the project’s current plan and resource allocation. Which PRINCE2® concept most directly addresses the need to modify the project’s management approach and controls to accommodate these new external requirements?
Correct
The core of this question lies in understanding how PRINCE2® handles the adaptation of its principles, themes, and processes to suit the specific project environment. PRINCE2 emphasizes tailoring. When a project faces significant changes in its external environment, such as new regulatory requirements impacting a construction project or a sudden shift in market demand for a software product, the project management team must adapt. This adaptation isn’t about discarding PRINCE2 but about applying its flexibility. The ‘Initiating a Project’ process, specifically the ‘Project Approach’ element within the Project Initiation Documentation (PID), is where the initial strategy for how the project will be managed is defined, including how it will be tailored. However, the ongoing management and adaptation occur throughout the project lifecycle, driven by the Management By Exception principle and the constant monitoring and control activities. The ‘Controlling a Stage’ and ‘Managing Product Delivery’ processes are where day-to-day adjustments are made. The ‘Managing a Stage Boundary’ process is crucial for reviewing the project’s progress and its continued suitability, which might necessitate changes to the approach. The ‘Directing a Project’ process, specifically the Project Board’s role, is where strategic decisions about adapting the project’s direction and management approach are made. The most appropriate PRINCE2 term for adjusting the project’s methodology and controls in response to external shifts, while maintaining adherence to the framework’s flexibility, is ‘tailoring’. Tailoring ensures that the project management approach is appropriate to the environment in which the project will be run, the scale, complexity, importance, capability, and risk. Therefore, when faced with substantial external environmental shifts, the project manager, with the Project Board’s approval, would review and re-tailor the project management approach to ensure continued relevance and effectiveness. This involves reassessing the application of PRINCE2 principles, themes, and processes.
Incorrect
The core of this question lies in understanding how PRINCE2® handles the adaptation of its principles, themes, and processes to suit the specific project environment. PRINCE2 emphasizes tailoring. When a project faces significant changes in its external environment, such as new regulatory requirements impacting a construction project or a sudden shift in market demand for a software product, the project management team must adapt. This adaptation isn’t about discarding PRINCE2 but about applying its flexibility. The ‘Initiating a Project’ process, specifically the ‘Project Approach’ element within the Project Initiation Documentation (PID), is where the initial strategy for how the project will be managed is defined, including how it will be tailored. However, the ongoing management and adaptation occur throughout the project lifecycle, driven by the Management By Exception principle and the constant monitoring and control activities. The ‘Controlling a Stage’ and ‘Managing Product Delivery’ processes are where day-to-day adjustments are made. The ‘Managing a Stage Boundary’ process is crucial for reviewing the project’s progress and its continued suitability, which might necessitate changes to the approach. The ‘Directing a Project’ process, specifically the Project Board’s role, is where strategic decisions about adapting the project’s direction and management approach are made. The most appropriate PRINCE2 term for adjusting the project’s methodology and controls in response to external shifts, while maintaining adherence to the framework’s flexibility, is ‘tailoring’. Tailoring ensures that the project management approach is appropriate to the environment in which the project will be run, the scale, complexity, importance, capability, and risk. Therefore, when faced with substantial external environmental shifts, the project manager, with the Project Board’s approval, would review and re-tailor the project management approach to ensure continued relevance and effectiveness. This involves reassessing the application of PRINCE2 principles, themes, and processes.
-
Question 6 of 30
6. Question
Consider a complex, multi-phase initiative aiming to develop and launch a novel sustainable energy solution. Midway through the second phase, a significant, unforeseen global policy change dramatically alters the market landscape for renewable energy technologies, directly impacting the projected demand and competitive positioning of the solution. This shift raises serious questions about the original rationale and expected financial returns. Which PRINCE2 theme requires the most immediate and thorough attention to determine the project’s continued viability and appropriate course of action?
Correct
The question asks to identify the most appropriate PRINCE2 theme to focus on when a project experiences a significant shift in market demand, necessitating a re-evaluation of its objectives and deliverables. This scenario directly impacts the project’s viability and its ability to deliver business justification. The Business Case theme is fundamental to PRINCE2 as it underpins the project’s existence by defining the reasons for undertaking it, the expected benefits, and the associated costs and risks. When market conditions change drastically, the original Business Case may no longer be valid, requiring a thorough review and potential revision. This review would involve assessing whether the project’s expected benefits are still achievable, if the costs remain justifiable, and if the risks have changed. Without a valid Business Case, the project loses its direction and justification. While other themes are important, they are often managed *in support of* the Business Case. For instance, the ‘Risk’ theme would be used to identify and manage the risks associated with the market shift, but the *decision* to continue, adapt, or terminate the project based on the revised business justification falls under the Business Case theme. The ‘Change’ theme deals with managing changes to the project, but the fundamental question of whether the project *should* change in response to market shifts is rooted in its business justification. The ‘Stakeholder’ theme is crucial for communication and engagement, but it doesn’t directly address the core issue of re-validating the project’s purpose. Therefore, the Business Case theme is the most pertinent for addressing a fundamental shift in market demand that challenges the project’s original objectives.
Incorrect
The question asks to identify the most appropriate PRINCE2 theme to focus on when a project experiences a significant shift in market demand, necessitating a re-evaluation of its objectives and deliverables. This scenario directly impacts the project’s viability and its ability to deliver business justification. The Business Case theme is fundamental to PRINCE2 as it underpins the project’s existence by defining the reasons for undertaking it, the expected benefits, and the associated costs and risks. When market conditions change drastically, the original Business Case may no longer be valid, requiring a thorough review and potential revision. This review would involve assessing whether the project’s expected benefits are still achievable, if the costs remain justifiable, and if the risks have changed. Without a valid Business Case, the project loses its direction and justification. While other themes are important, they are often managed *in support of* the Business Case. For instance, the ‘Risk’ theme would be used to identify and manage the risks associated with the market shift, but the *decision* to continue, adapt, or terminate the project based on the revised business justification falls under the Business Case theme. The ‘Change’ theme deals with managing changes to the project, but the fundamental question of whether the project *should* change in response to market shifts is rooted in its business justification. The ‘Stakeholder’ theme is crucial for communication and engagement, but it doesn’t directly address the core issue of re-validating the project’s purpose. Therefore, the Business Case theme is the most pertinent for addressing a fundamental shift in market demand that challenges the project’s original objectives.
-
Question 7 of 30
7. Question
Following the approval of the Project Brief for the ‘Aurora’ initiative, a critical external regulatory body has introduced new compliance mandates that fundamentally alter the operational parameters of the intended solution. This necessitates a significant revision to the project’s scope and the expected benefits outlined in the initial Business Case. As the Project Manager, what is the most appropriate course of action to maintain PRINCE2 governance and ensure the project remains viable?
Correct
The core of this question lies in understanding how PRINCE2 addresses changes during the ‘Initiating a Project’ process, specifically concerning the Project Brief and the Business Case. The Project Brief, once approved, forms the basis for the Project Initiation Documentation (PID). The PID contains the Business Case, which details the justification for the project. If a significant change occurs that impacts the project’s viability or the original justification, it necessitates a formal change control process. This involves assessing the impact of the change, potentially revising the Business Case, and seeking approval for the revised Business Case before proceeding. The Project Board is the ultimate authority for approving significant changes that affect the project’s objectives or viability, as outlined in the PRINCE2 principles. Adjusting the Project Brief alone without a revised Business Case and Board approval would bypass critical governance. Therefore, revising the Business Case and obtaining Project Board approval for the changes to the Project Brief is the correct approach to maintain project control and ensure continued justification.
Incorrect
The core of this question lies in understanding how PRINCE2 addresses changes during the ‘Initiating a Project’ process, specifically concerning the Project Brief and the Business Case. The Project Brief, once approved, forms the basis for the Project Initiation Documentation (PID). The PID contains the Business Case, which details the justification for the project. If a significant change occurs that impacts the project’s viability or the original justification, it necessitates a formal change control process. This involves assessing the impact of the change, potentially revising the Business Case, and seeking approval for the revised Business Case before proceeding. The Project Board is the ultimate authority for approving significant changes that affect the project’s objectives or viability, as outlined in the PRINCE2 principles. Adjusting the Project Brief alone without a revised Business Case and Board approval would bypass critical governance. Therefore, revising the Business Case and obtaining Project Board approval for the changes to the Project Brief is the correct approach to maintain project control and ensure continued justification.
-
Question 8 of 30
8. Question
An established project, aimed at modernizing a legacy financial system, is facing substantial pressure from key operational stakeholders to incorporate advanced predictive analytics features. These features were not part of the original scope, and their integration would necessitate significant changes to the project’s timeline, budget, and resource allocation. During recent stage reviews, the Project Manager has reported a dip in team enthusiasm and a marked increase in the frequency of defect re-testing, suggesting potential quality compromises and a strained team dynamic. What fundamental PRINCE2 principle should be most critically reviewed and potentially re-affirmed or revised by the Project Board in response to this situation?
Correct
The scenario describes a project experiencing significant scope creep due to emergent stakeholder requirements that were not anticipated during the initiation phase. The project board has observed a decline in team morale and a noticeable increase in rework, indicating potential issues with the project’s control mechanisms and the Project Manager’s ability to manage expectations and changes effectively.
In PRINCE2, the principle of “continued business justification” is fundamental. When a project’s objectives or scope significantly deviate from the original business case, or if the justification for continuing the project weakens, it directly impacts this principle. The observed issues—unforeseen requirements, scope creep, declining morale, and increased rework—all suggest that the project’s viability and alignment with the business case are now questionable.
The “Manage by Exception” principle dictates that the project board should only be involved when tolerances are forecast to be exceeded. However, the *impact* of the emerging requirements on the project’s viability and the *need for a revised business case* requires proactive escalation and decision-making by the project board, rather than waiting for specific tolerances to be breached. The Project Manager’s role is to monitor these changes and their impact, and to escalate when the project’s direction or justification is threatened.
The “Focus on Products” principle ensures that the project is delivered based on defined products and their quality criteria. While this is important, it doesn’t directly address the *strategic decision* of whether to continue the project in its altered state. “Organize by Stages” is a control mechanism that breaks the project down, but the core issue here is the fundamental justification for the project’s existence and direction. “Tailor PRINCE2 to suit the project environment” is a guiding principle that influences how PRINCE2 is applied, but it doesn’t dictate the specific action needed when the business justification is challenged.
Therefore, the most appropriate action, considering the impact on the project’s viability and the need for a strategic re-evaluation, is to revisit the business justification. This involves assessing whether the original business case still holds true given the changes, and if not, whether a revised business case is required to continue. This directly aligns with the “continued business justification” principle and the need for the project board to make informed decisions about the project’s future.
Incorrect
The scenario describes a project experiencing significant scope creep due to emergent stakeholder requirements that were not anticipated during the initiation phase. The project board has observed a decline in team morale and a noticeable increase in rework, indicating potential issues with the project’s control mechanisms and the Project Manager’s ability to manage expectations and changes effectively.
In PRINCE2, the principle of “continued business justification” is fundamental. When a project’s objectives or scope significantly deviate from the original business case, or if the justification for continuing the project weakens, it directly impacts this principle. The observed issues—unforeseen requirements, scope creep, declining morale, and increased rework—all suggest that the project’s viability and alignment with the business case are now questionable.
The “Manage by Exception” principle dictates that the project board should only be involved when tolerances are forecast to be exceeded. However, the *impact* of the emerging requirements on the project’s viability and the *need for a revised business case* requires proactive escalation and decision-making by the project board, rather than waiting for specific tolerances to be breached. The Project Manager’s role is to monitor these changes and their impact, and to escalate when the project’s direction or justification is threatened.
The “Focus on Products” principle ensures that the project is delivered based on defined products and their quality criteria. While this is important, it doesn’t directly address the *strategic decision* of whether to continue the project in its altered state. “Organize by Stages” is a control mechanism that breaks the project down, but the core issue here is the fundamental justification for the project’s existence and direction. “Tailor PRINCE2 to suit the project environment” is a guiding principle that influences how PRINCE2 is applied, but it doesn’t dictate the specific action needed when the business justification is challenged.
Therefore, the most appropriate action, considering the impact on the project’s viability and the need for a strategic re-evaluation, is to revisit the business justification. This involves assessing whether the original business case still holds true given the changes, and if not, whether a revised business case is required to continue. This directly aligns with the “continued business justification” principle and the need for the project board to make informed decisions about the project’s future.
-
Question 9 of 30
9. Question
During the execution of a complex digital transformation initiative aimed at enhancing customer engagement, an unexpected and rapid shift in consumer behaviour, driven by emerging technological platforms, renders the project’s primary deliverable significantly less relevant. The Project Manager, Elara Vance, must advise the Project Board on the next steps. Which PRINCE2 principle should Elara primarily rely upon to guide her recommendation and the subsequent decision-making process regarding the project’s continuation or adaptation?
Correct
The question asks to identify the most appropriate PRINCE2 principle to guide the Project Manager’s actions when faced with a significant, unforeseen change in market demand that necessitates a fundamental shift in the project’s objectives and deliverables. This scenario represents a situation where the project’s original rationale might be invalidated or significantly altered.
* **Continued Business Justification:** This principle requires that the project continues to have a valid business case throughout its lifecycle. When market demand shifts dramatically, the existing business case needs to be re-evaluated. If the project is no longer aligned with current business needs or market opportunities, it may need to be stopped or fundamentally altered. The Project Manager’s responsibility is to ensure that the project remains viable.
* **Manage by Stages:** This principle breaks the project into manageable stages, allowing for review and decision-making at the end of each stage. While relevant for controlling the project, it doesn’t directly address the fundamental decision of whether to continue or pivot due to a drastic external change.
* **Manage by Exception:** This principle focuses on managing deviations from planned tolerances. While the change in market demand is an exception, the core issue is the continued viability of the project’s objectives, not just managing deviations within the current plan.
* **Focus on Products:** This principle emphasizes defining and delivering the project’s products. While important, it doesn’t provide the overarching guidance for adapting to a complete shift in what those products should be or if they are still relevant.Given the scenario, the most critical principle is **Continued Business Justification**. The Project Manager must ensure that the project’s objectives and expected benefits are still valid in light of the new market conditions. This might lead to a decision to revise the project brief, request a new business case, or even terminate the project if it no longer serves the business. The Project Manager’s role is to escalate this situation to the Project Board, providing the necessary information to make an informed decision about the project’s future based on its ongoing business justification.
Incorrect
The question asks to identify the most appropriate PRINCE2 principle to guide the Project Manager’s actions when faced with a significant, unforeseen change in market demand that necessitates a fundamental shift in the project’s objectives and deliverables. This scenario represents a situation where the project’s original rationale might be invalidated or significantly altered.
* **Continued Business Justification:** This principle requires that the project continues to have a valid business case throughout its lifecycle. When market demand shifts dramatically, the existing business case needs to be re-evaluated. If the project is no longer aligned with current business needs or market opportunities, it may need to be stopped or fundamentally altered. The Project Manager’s responsibility is to ensure that the project remains viable.
* **Manage by Stages:** This principle breaks the project into manageable stages, allowing for review and decision-making at the end of each stage. While relevant for controlling the project, it doesn’t directly address the fundamental decision of whether to continue or pivot due to a drastic external change.
* **Manage by Exception:** This principle focuses on managing deviations from planned tolerances. While the change in market demand is an exception, the core issue is the continued viability of the project’s objectives, not just managing deviations within the current plan.
* **Focus on Products:** This principle emphasizes defining and delivering the project’s products. While important, it doesn’t provide the overarching guidance for adapting to a complete shift in what those products should be or if they are still relevant.Given the scenario, the most critical principle is **Continued Business Justification**. The Project Manager must ensure that the project’s objectives and expected benefits are still valid in light of the new market conditions. This might lead to a decision to revise the project brief, request a new business case, or even terminate the project if it no longer serves the business. The Project Manager’s role is to escalate this situation to the Project Board, providing the necessary information to make an informed decision about the project’s future based on its ongoing business justification.
-
Question 10 of 30
10. Question
A PRINCE2 project, aimed at developing a novel sustainable energy storage system, is experiencing significant pressure from key stakeholders to incorporate additional features and functionalities not originally specified. The Project Manager has observed that these requests, while potentially beneficial, are causing delays and increasing costs, leading to a divergence from the approved project plan. The Project Board has expressed concern about the project’s adherence to its defined scope and the potential impact on the business case. Considering the principles of PRINCE2, what is the most effective immediate action to regain control and manage this situation?
Correct
The scenario describes a project experiencing scope creep due to evolving stakeholder requirements and a lack of rigorous change control. The Project Board is concerned about the project’s deviation from its original objectives and the potential impact on its viability. In PRINCE2, the primary mechanism for controlling deviations from the project plan, including scope creep, is the Change Control Approach, which is detailed in the Project Initiation Documentation (PID). This approach outlines how changes will be identified, assessed, and approved or rejected. The Project Manager is responsible for managing the Change Control approach, which includes ensuring that all proposed changes are logged, assessed for impact (on time, cost, quality, scope, risk, and benefits), and then presented to the appropriate authority (often the Change Authority or Project Board) for a decision. If a change is approved, it will likely result in a revised baseline for the affected project aspect, which then needs to be re-baselined. The question asks about the *most* effective way to address the situation described, which is a reactive measure to an ongoing problem. While monitoring progress against the plan is crucial, it’s a continuous activity, not a specific action to resolve scope creep. Similarly, reviewing the Business Case is important for the overall project viability but doesn’t directly address the *process* of managing the scope changes themselves. The most direct and effective PRINCE2 control for managing scope creep is to ensure the Change Control Approach is being followed and that any approved changes are properly managed, including re-baselining if necessary. Therefore, the most appropriate action is to ensure the Change Control Approach is robustly implemented and that any approved changes are re-baselined.
Incorrect
The scenario describes a project experiencing scope creep due to evolving stakeholder requirements and a lack of rigorous change control. The Project Board is concerned about the project’s deviation from its original objectives and the potential impact on its viability. In PRINCE2, the primary mechanism for controlling deviations from the project plan, including scope creep, is the Change Control Approach, which is detailed in the Project Initiation Documentation (PID). This approach outlines how changes will be identified, assessed, and approved or rejected. The Project Manager is responsible for managing the Change Control approach, which includes ensuring that all proposed changes are logged, assessed for impact (on time, cost, quality, scope, risk, and benefits), and then presented to the appropriate authority (often the Change Authority or Project Board) for a decision. If a change is approved, it will likely result in a revised baseline for the affected project aspect, which then needs to be re-baselined. The question asks about the *most* effective way to address the situation described, which is a reactive measure to an ongoing problem. While monitoring progress against the plan is crucial, it’s a continuous activity, not a specific action to resolve scope creep. Similarly, reviewing the Business Case is important for the overall project viability but doesn’t directly address the *process* of managing the scope changes themselves. The most direct and effective PRINCE2 control for managing scope creep is to ensure the Change Control Approach is being followed and that any approved changes are properly managed, including re-baselining if necessary. Therefore, the most appropriate action is to ensure the Change Control Approach is robustly implemented and that any approved changes are re-baselined.
-
Question 11 of 30
11. Question
A PRINCE2 project focused on developing a novel renewable energy system has encountered unforeseen technical complexities. The latest progress report indicates a potential delay of 25% beyond the agreed-upon time tolerance for the current phase, and a projected cost overrun of 15% against the phase budget, both exceeding their respective tolerances. The Project Manager has prepared an Exception Report detailing these deviations and proposing several mitigation strategies. Which PRINCE2 body is primarily responsible for reviewing the Exception Report and deciding on the subsequent course of action for the project?
Correct
The PRINCE2 methodology emphasizes a management-by-exception approach, which relies on defined tolerances for project objectives at each management level. When a project exceeds these tolerances, it triggers an exception. The Project Board is responsible for reviewing exceptions and deciding on appropriate actions. In this scenario, the project is experiencing a significant deviation in its delivery schedule, exceeding the agreed-upon tolerance for time. The Project Manager, following the PRINCE2 principles, must report this deviation as an Exception Report to the Project Board. The Project Board’s role is to analyze the impact of the delay, consider potential remedies (such as increasing resources or adjusting scope, if within their authority), and decide whether to continue the project as is, with modifications, or even terminate it. The key is that the Project Board is the ultimate decision-making authority for handling exceptions that go beyond the Project Manager’s delegated authority. The question tests the understanding of who is responsible for deciding on actions when project tolerances are breached, which is a core aspect of PRINCE2’s control mechanisms.
Incorrect
The PRINCE2 methodology emphasizes a management-by-exception approach, which relies on defined tolerances for project objectives at each management level. When a project exceeds these tolerances, it triggers an exception. The Project Board is responsible for reviewing exceptions and deciding on appropriate actions. In this scenario, the project is experiencing a significant deviation in its delivery schedule, exceeding the agreed-upon tolerance for time. The Project Manager, following the PRINCE2 principles, must report this deviation as an Exception Report to the Project Board. The Project Board’s role is to analyze the impact of the delay, consider potential remedies (such as increasing resources or adjusting scope, if within their authority), and decide whether to continue the project as is, with modifications, or even terminate it. The key is that the Project Board is the ultimate decision-making authority for handling exceptions that go beyond the Project Manager’s delegated authority. The question tests the understanding of who is responsible for deciding on actions when project tolerances are breached, which is a core aspect of PRINCE2’s control mechanisms.
-
Question 12 of 30
12. Question
A PRINCE2 project, focused on developing a novel AI-driven diagnostic tool for a niche medical field, is facing significant pressure to incorporate new functionalities discovered through early user feedback. The Project Board, however, is primarily communicating with the Project Manager via ad-hoc email requests for status updates on specific development tasks, rather than engaging in broader strategic discussions about the evolving project vision. The Project Manager has noted a consistent pattern of reactive decision-making from the Board, often approving minor scope adjustments without a clear overarching strategic rationale. What is the most effective course of action for the Project Manager to ensure the project remains aligned with its original business case and strategic objectives?
Correct
The scenario describes a project experiencing scope creep due to evolving stakeholder needs, which is a common challenge. The project manager is observing a lack of proactive engagement from the Project Board regarding strategic direction and is instead receiving reactive directives on specific tasks. This indicates a potential breakdown in the Project Board’s oversight and strategic guidance. In PRINCE2, the Project Board is responsible for providing overall direction and strategic control. When the Project Board is not actively involved in guiding the project’s strategic direction, and instead focuses on tactical task management, it suggests a failure in their role of providing direction and control. The Project Manager’s actions should focus on re-establishing this strategic oversight. Requesting a strategic review session with the Project Board to redefine the project’s objectives and scope in light of new information is the most appropriate action. This aligns with the PRINCE2 principles of “Continued Business Justification” and “Manage by Stages,” where the Project Board reviews progress and provides direction at key points. Furthermore, it addresses the Project Manager’s need for clear strategic guidance to manage the evolving requirements and prevent further scope creep. The Project Manager should not solely rely on informal communication or attempt to manage the strategic direction independently. The emphasis on “Manage by Exception” means the Project Board should be informed of deviations from the plan and empowered to make strategic decisions, not just approve task-level changes. Therefore, initiating a formal discussion to realign the project’s strategy is paramount.
Incorrect
The scenario describes a project experiencing scope creep due to evolving stakeholder needs, which is a common challenge. The project manager is observing a lack of proactive engagement from the Project Board regarding strategic direction and is instead receiving reactive directives on specific tasks. This indicates a potential breakdown in the Project Board’s oversight and strategic guidance. In PRINCE2, the Project Board is responsible for providing overall direction and strategic control. When the Project Board is not actively involved in guiding the project’s strategic direction, and instead focuses on tactical task management, it suggests a failure in their role of providing direction and control. The Project Manager’s actions should focus on re-establishing this strategic oversight. Requesting a strategic review session with the Project Board to redefine the project’s objectives and scope in light of new information is the most appropriate action. This aligns with the PRINCE2 principles of “Continued Business Justification” and “Manage by Stages,” where the Project Board reviews progress and provides direction at key points. Furthermore, it addresses the Project Manager’s need for clear strategic guidance to manage the evolving requirements and prevent further scope creep. The Project Manager should not solely rely on informal communication or attempt to manage the strategic direction independently. The emphasis on “Manage by Exception” means the Project Board should be informed of deviations from the plan and empowered to make strategic decisions, not just approve task-level changes. Therefore, initiating a formal discussion to realign the project’s strategy is paramount.
-
Question 13 of 30
13. Question
A project to develop a new software solution for a niche market is underway. During the ‘Initiating a Project’ process, the Project Manager discovers that significant shifts in competitor offerings and customer adoption patterns have occurred since the initial market analysis, rendering the original Business Case’s assumptions about market share and profitability no longer tenable. The project is still considered strategically important, but the original justification requires substantial re-evaluation. What is the most appropriate PRINCE2 action for the Project Manager to take in this situation?
Correct
The PRINCE2 methodology emphasizes the importance of effective communication throughout the project lifecycle. In this scenario, the Project Manager (PM) is facing a situation where the Business Case, a key document, is no longer aligned with the evolving market conditions. The Business Case is the foundation upon which the project’s justification and objectives are built. When it becomes obsolete, it fundamentally undermines the project’s viability and direction.
The question asks about the *most* appropriate PRINCE2 action to take. Let’s consider the options:
* **Initiating a new project:** While a complete pivot might eventually lead to a new project, initiating one immediately without proper assessment is premature and potentially wasteful. A new project requires a Project Mandate and Initiation Stage, which are significant undertakings.
* **Revising the Project Brief:** The Project Brief is a summary of the project’s purpose, objectives, and scope, derived from the Business Case. If the Business Case is invalid, the Project Brief, which relies on it, is also likely to be misaligned. Revising the Project Brief alone without addressing the root cause (the Business Case) would be a superficial fix.
* **Requesting a Project Exception Report:** An Exception Report is used when the project is forecast to deviate from its plan beyond agreed tolerances. While the business case becoming obsolete *will* lead to deviations, the primary issue here is the fundamental validity of the project’s justification, not just a deviation from an existing plan. An Exception Report is a response to a deviation, not a proactive measure to address a fundamental flaw in the project’s premise.
* **Revising the Business Case:** The Business Case is the critical document that justifies the project. If market conditions have changed, rendering the original Business Case invalid, the most direct and PRINCE2-aligned action is to revise the Business Case to reflect the new reality. This revision would then inform subsequent project documentation, including the Project Brief and potentially the Project Initiation Documentation (PID). The PRINCE2 principle of “Continued Business Justification” mandates that the Business Case remains valid throughout the project. When it ceases to be valid, it must be updated or the project terminated. Therefore, revising the Business Case is the most appropriate initial step to re-establish the project’s viability and direction.The core issue is the loss of continued business justification. PRINCE2’s principle of “Continued Business Justification” dictates that the Business Case must remain valid throughout the project. If the market conditions have shifted such that the original Business Case is no longer accurate or relevant, this principle is being violated. The most direct and effective PRINCE2 response is to address this fundamental issue by revising the Business Case. This revised Business Case will then form the basis for any necessary updates to other project documentation, such as the Project Brief, and will guide decision-making regarding the project’s future. Initiating a new project is too drastic a step without first attempting to re-justify the current one. Revising the Project Brief alone would be a superficial measure that doesn’t address the root cause of the misalignment. An Exception Report is for deviations from an agreed plan, not for a fundamental loss of business justification.
Incorrect
The PRINCE2 methodology emphasizes the importance of effective communication throughout the project lifecycle. In this scenario, the Project Manager (PM) is facing a situation where the Business Case, a key document, is no longer aligned with the evolving market conditions. The Business Case is the foundation upon which the project’s justification and objectives are built. When it becomes obsolete, it fundamentally undermines the project’s viability and direction.
The question asks about the *most* appropriate PRINCE2 action to take. Let’s consider the options:
* **Initiating a new project:** While a complete pivot might eventually lead to a new project, initiating one immediately without proper assessment is premature and potentially wasteful. A new project requires a Project Mandate and Initiation Stage, which are significant undertakings.
* **Revising the Project Brief:** The Project Brief is a summary of the project’s purpose, objectives, and scope, derived from the Business Case. If the Business Case is invalid, the Project Brief, which relies on it, is also likely to be misaligned. Revising the Project Brief alone without addressing the root cause (the Business Case) would be a superficial fix.
* **Requesting a Project Exception Report:** An Exception Report is used when the project is forecast to deviate from its plan beyond agreed tolerances. While the business case becoming obsolete *will* lead to deviations, the primary issue here is the fundamental validity of the project’s justification, not just a deviation from an existing plan. An Exception Report is a response to a deviation, not a proactive measure to address a fundamental flaw in the project’s premise.
* **Revising the Business Case:** The Business Case is the critical document that justifies the project. If market conditions have changed, rendering the original Business Case invalid, the most direct and PRINCE2-aligned action is to revise the Business Case to reflect the new reality. This revision would then inform subsequent project documentation, including the Project Brief and potentially the Project Initiation Documentation (PID). The PRINCE2 principle of “Continued Business Justification” mandates that the Business Case remains valid throughout the project. When it ceases to be valid, it must be updated or the project terminated. Therefore, revising the Business Case is the most appropriate initial step to re-establish the project’s viability and direction.The core issue is the loss of continued business justification. PRINCE2’s principle of “Continued Business Justification” dictates that the Business Case must remain valid throughout the project. If the market conditions have shifted such that the original Business Case is no longer accurate or relevant, this principle is being violated. The most direct and effective PRINCE2 response is to address this fundamental issue by revising the Business Case. This revised Business Case will then form the basis for any necessary updates to other project documentation, such as the Project Brief, and will guide decision-making regarding the project’s future. Initiating a new project is too drastic a step without first attempting to re-justify the current one. Revising the Project Brief alone would be a superficial measure that doesn’t address the root cause of the misalignment. An Exception Report is for deviations from an agreed plan, not for a fundamental loss of business justification.
-
Question 14 of 30
14. Question
A PRINCE2 project, initiated to develop a new financial reporting system compliant with upcoming international regulations, is midway through its second management stage. During a recent stakeholder review, it was revealed that a crucial market analysis, conducted after the project’s initiation, suggests significant shifts in customer behaviour that could impact the system’s long-term adoption. Simultaneously, a new draft of the international regulations has been released, containing several clauses that were not anticipated and will necessitate substantial rework of the system’s core architecture. The project manager, recognizing the potential for significant deviation from the original plan and business case, needs to determine the most effective PRINCE2 approach to manage these developments. Which PRINCE2 principle most directly guides the project manager’s immediate next steps in response to these converging challenges?
Correct
The scenario describes a project facing significant scope creep due to evolving regulatory requirements and a key stakeholder’s insistence on incorporating new market analysis findings. The project manager needs to address this without immediately resorting to a full-blown project closure or a simple refusal, as per PRINCE2 principles.
The PRINCE2 principle of “continued business justification” is paramount here. If the new requirements fundamentally alter the business case, the project’s viability needs re-evaluation. The principle of “manage by stages” dictates that the project is planned and controlled in manageable phases. The current situation necessitates a review at the end of the current stage.
The principle of “manage by exception” means that the project board is only informed of deviations from agreed tolerances. The scope creep described is a significant deviation. The principle of “focus on products” means that the project must clearly define its deliverables and ensure they meet the required quality. The new requirements impact the products.
The principle of “organize for quality” emphasizes defining roles and responsibilities for quality. The principle of “tailor to suit the project environment” suggests adapting the methodology. The principle of “manage by stages” is the most relevant for handling this specific situation of significant change that impacts the project’s direction and viability, requiring a formal checkpoint before proceeding.
Therefore, the most appropriate action is to review the project’s viability and potentially re-plan based on the new information, which aligns with managing by stages and ensuring continued business justification. The project manager should present the impact of the changes to the Project Board at the end of the current stage to decide whether to continue, revise, or terminate the project. This decision-making process inherently involves assessing the business case, which is a core activity at stage boundaries.
Incorrect
The scenario describes a project facing significant scope creep due to evolving regulatory requirements and a key stakeholder’s insistence on incorporating new market analysis findings. The project manager needs to address this without immediately resorting to a full-blown project closure or a simple refusal, as per PRINCE2 principles.
The PRINCE2 principle of “continued business justification” is paramount here. If the new requirements fundamentally alter the business case, the project’s viability needs re-evaluation. The principle of “manage by stages” dictates that the project is planned and controlled in manageable phases. The current situation necessitates a review at the end of the current stage.
The principle of “manage by exception” means that the project board is only informed of deviations from agreed tolerances. The scope creep described is a significant deviation. The principle of “focus on products” means that the project must clearly define its deliverables and ensure they meet the required quality. The new requirements impact the products.
The principle of “organize for quality” emphasizes defining roles and responsibilities for quality. The principle of “tailor to suit the project environment” suggests adapting the methodology. The principle of “manage by stages” is the most relevant for handling this specific situation of significant change that impacts the project’s direction and viability, requiring a formal checkpoint before proceeding.
Therefore, the most appropriate action is to review the project’s viability and potentially re-plan based on the new information, which aligns with managing by stages and ensuring continued business justification. The project manager should present the impact of the changes to the Project Board at the end of the current stage to decide whether to continue, revise, or terminate the project. This decision-making process inherently involves assessing the business case, which is a core activity at stage boundaries.
-
Question 15 of 30
15. Question
Consider a scenario where the Project Board of the ‘SynergyStream’ initiative, focused on implementing a bespoke customer analytics platform, is informed of an impending strategic merger with a competitor. This merger will significantly alter the market landscape and the intended user base for the platform. The project is currently at the end of its ‘Initiation’ stage, with the ‘Plan Project’ stage already approved, and the ‘Design’ stage about to commence. What action should the Project Board prioritize to ensure continued project viability and alignment with the new corporate direction?
Correct
The core of this question lies in understanding how PRINCE2® principles and themes are applied during a significant organizational shift, specifically focusing on the Project Board’s role in managing change and ensuring continued project alignment with business objectives. The scenario describes a situation where a project, initially approved with a specific scope for a new customer relationship management (CRM) system, is facing a strategic pivot due to an unforeseen merger. The Project Board must decide how to proceed.
The key PRINCE2® concepts at play here are:
* **Continued Business Justification:** The Business Case, a cornerstone of PRINCE2®, must remain valid. The merger fundamentally alters the business context, potentially invalidating the original Business Case.
* **Manage by Stages:** Projects are broken down into manageable stages, allowing for review and decision-making at key points. The merger necessitates a review at the end of the current stage.
* **Manage by Exception:** The Project Board oversees progress and intervenes only when tolerances are forecast to be exceeded. However, a strategic shift of this magnitude requires proactive management, not just exception handling.
* **The Project Board’s Role:** The Project Board is responsible for directing the project, providing strategic guidance, and ensuring the project remains aligned with business objectives. This includes making critical decisions about scope, priorities, and even project continuation.
* **Themes:** Specifically, the Business Case theme is most impacted, but others like Risk, Change, and Stakeholders are also highly relevant.Given the merger, the original Business Case for the CRM system might no longer be relevant or may need substantial revision. The project’s objectives, scope, and expected benefits could all be affected. Therefore, the most appropriate PRINCE2® action for the Project Board is to request a revised Business Case and then decide whether to continue the project based on this updated justification. This ensures that any continued investment is aligned with the new organizational strategy and market position.
The calculation, in this conceptual context, is not a numerical one but rather a logical progression of PRINCE2® governance. The steps are:
1. Recognize the significant change impacting the project’s Business Case.
2. Recall the Project Board’s responsibility for ensuring continued business justification.
3. Determine the PRINCE2® mechanism for re-evaluating justification: a revised Business Case.
4. Conclude that the Project Board must then decide the project’s fate based on this revised justification.Therefore, the action that most directly addresses the PRINCE2® governance for this situation is to await and review the revised Business Case before making a decision.
Incorrect
The core of this question lies in understanding how PRINCE2® principles and themes are applied during a significant organizational shift, specifically focusing on the Project Board’s role in managing change and ensuring continued project alignment with business objectives. The scenario describes a situation where a project, initially approved with a specific scope for a new customer relationship management (CRM) system, is facing a strategic pivot due to an unforeseen merger. The Project Board must decide how to proceed.
The key PRINCE2® concepts at play here are:
* **Continued Business Justification:** The Business Case, a cornerstone of PRINCE2®, must remain valid. The merger fundamentally alters the business context, potentially invalidating the original Business Case.
* **Manage by Stages:** Projects are broken down into manageable stages, allowing for review and decision-making at key points. The merger necessitates a review at the end of the current stage.
* **Manage by Exception:** The Project Board oversees progress and intervenes only when tolerances are forecast to be exceeded. However, a strategic shift of this magnitude requires proactive management, not just exception handling.
* **The Project Board’s Role:** The Project Board is responsible for directing the project, providing strategic guidance, and ensuring the project remains aligned with business objectives. This includes making critical decisions about scope, priorities, and even project continuation.
* **Themes:** Specifically, the Business Case theme is most impacted, but others like Risk, Change, and Stakeholders are also highly relevant.Given the merger, the original Business Case for the CRM system might no longer be relevant or may need substantial revision. The project’s objectives, scope, and expected benefits could all be affected. Therefore, the most appropriate PRINCE2® action for the Project Board is to request a revised Business Case and then decide whether to continue the project based on this updated justification. This ensures that any continued investment is aligned with the new organizational strategy and market position.
The calculation, in this conceptual context, is not a numerical one but rather a logical progression of PRINCE2® governance. The steps are:
1. Recognize the significant change impacting the project’s Business Case.
2. Recall the Project Board’s responsibility for ensuring continued business justification.
3. Determine the PRINCE2® mechanism for re-evaluating justification: a revised Business Case.
4. Conclude that the Project Board must then decide the project’s fate based on this revised justification.Therefore, the action that most directly addresses the PRINCE2® governance for this situation is to await and review the revised Business Case before making a decision.
-
Question 16 of 30
16. Question
A critical component for a high-profile software development project, adhering to PRINCE2® methodology, is exclusively sourced from a single, specialized supplier. Midway through the execution phase, this supplier unexpectedly declares bankruptcy and ceases all operations, making the component unobtainable through the original channel. The project’s quality criteria for this component are stringent, and alternative components would require significant rework and potentially compromise the end-product’s performance, which is a key stakeholder requirement. The Project Manager has assessed that the impact of this event, if unaddressed, will exceed the stage tolerances for both quality and time. What is the most appropriate PRINCE2®-aligned action for the Project Manager to take immediately?
Correct
The core of this question lies in understanding how PRINCE2® principles guide the response to unforeseen circumstances, specifically in the context of project scope and quality. The PRINCE2 principle of “Manage by Stages” dictates that a project is divided into manageable segments, with review points at the end of each stage. This allows for control and the ability to adapt. The principle of “Focus on Products” emphasizes defining and delivering the project’s products, including their quality requirements. When a critical supplier for a key component becomes unavailable, the project manager must first assess the impact on the project’s products and the defined quality criteria. The PRINCE2 principle of “Manage by Exception” allows the project manager to escalate issues that exceed predefined tolerances, thereby involving higher levels of management.
In this scenario, the unavailability of the supplier directly impacts the ability to deliver a key product within the agreed-upon scope and quality. The project manager’s immediate responsibility is to investigate alternative solutions that maintain the project’s objectives as much as possible. This involves assessing the impact on scope, time, cost, and quality. If the original supplier was the only viable option for achieving the specified quality, then a deviation from the original plan is inevitable.
The PRINCE2 approach would involve the Project Manager assessing the impact on the project’s products and tolerances. If the deviation from the original plan (due to supplier unavailability impacting product quality or delivery) exceeds the agreed tolerances for the current stage or the project as a whole, the Project Manager must raise an Exception Report to the Project Board. This report would detail the issue, its impact, and recommended options. The Project Board, in line with the “Directing a Project” process, would then decide on the course of action, which could include approving changes to scope, quality, time, or cost, or even terminating the project if it’s no longer viable. The question asks what the *most* appropriate action is, focusing on the immediate, principle-driven response. Option D, initiating a formal Exception Report, directly aligns with the “Manage by Exception” principle and the structured approach to handling deviations that could impact project objectives or tolerances, allowing for informed decision-making by the Project Board.
Incorrect
The core of this question lies in understanding how PRINCE2® principles guide the response to unforeseen circumstances, specifically in the context of project scope and quality. The PRINCE2 principle of “Manage by Stages” dictates that a project is divided into manageable segments, with review points at the end of each stage. This allows for control and the ability to adapt. The principle of “Focus on Products” emphasizes defining and delivering the project’s products, including their quality requirements. When a critical supplier for a key component becomes unavailable, the project manager must first assess the impact on the project’s products and the defined quality criteria. The PRINCE2 principle of “Manage by Exception” allows the project manager to escalate issues that exceed predefined tolerances, thereby involving higher levels of management.
In this scenario, the unavailability of the supplier directly impacts the ability to deliver a key product within the agreed-upon scope and quality. The project manager’s immediate responsibility is to investigate alternative solutions that maintain the project’s objectives as much as possible. This involves assessing the impact on scope, time, cost, and quality. If the original supplier was the only viable option for achieving the specified quality, then a deviation from the original plan is inevitable.
The PRINCE2 approach would involve the Project Manager assessing the impact on the project’s products and tolerances. If the deviation from the original plan (due to supplier unavailability impacting product quality or delivery) exceeds the agreed tolerances for the current stage or the project as a whole, the Project Manager must raise an Exception Report to the Project Board. This report would detail the issue, its impact, and recommended options. The Project Board, in line with the “Directing a Project” process, would then decide on the course of action, which could include approving changes to scope, quality, time, or cost, or even terminating the project if it’s no longer viable. The question asks what the *most* appropriate action is, focusing on the immediate, principle-driven response. Option D, initiating a formal Exception Report, directly aligns with the “Manage by Exception” principle and the structured approach to handling deviations that could impact project objectives or tolerances, allowing for informed decision-making by the Project Board.
-
Question 17 of 30
17. Question
A project is experiencing persistent scope deviations driven by frequent, informal directive changes from the Project Board members to the Project Manager. These directives, while seemingly minor individually, are cumulatively leading to significant scope creep and jeopardizing the project’s adherence to its approved tolerances for time and cost. The Project Manager has attempted to address these through informal discussions, but the pattern continues. What fundamental PRINCE2 principle is most critically being undermined by the Project Board’s actions, and what is the most appropriate next step for the Project Manager to take within the PRINCE2 framework to rectify this situation?
Correct
The PRINCE2 methodology emphasizes the importance of a Project Board comprising at least an Executive, a Senior User, and a Senior Supplier. The question describes a scenario where the Project Board is consistently overriding the Project Manager’s decisions regarding the project’s scope, leading to scope creep and impacting delivery timelines. This directly relates to the PRINCE2 principle of “Continued Business Justification,” which requires the project to remain viable and aligned with business objectives throughout its lifecycle. When the Project Board repeatedly alters the scope without a formal Change Control approach, it undermines the project’s justification and can lead to significant deviations from the original business case. Furthermore, it highlights a breakdown in the PRINCE2 principle of “Defined Roles and Responsibilities,” as the Project Board is not fulfilling its oversight role effectively and is instead micromanaging operational aspects, which should primarily be the responsibility of the Project Manager. The correct approach, as per PRINCE2, would involve the Project Manager escalating these deviations to the Project Board, clearly articulating the impact on the business case and tolerances, and seeking a formal decision on scope changes through the established Change Control Procedure. The Project Board’s actions, as described, indicate a failure to adhere to the defined governance structure and the principles of controlled scope management.
Incorrect
The PRINCE2 methodology emphasizes the importance of a Project Board comprising at least an Executive, a Senior User, and a Senior Supplier. The question describes a scenario where the Project Board is consistently overriding the Project Manager’s decisions regarding the project’s scope, leading to scope creep and impacting delivery timelines. This directly relates to the PRINCE2 principle of “Continued Business Justification,” which requires the project to remain viable and aligned with business objectives throughout its lifecycle. When the Project Board repeatedly alters the scope without a formal Change Control approach, it undermines the project’s justification and can lead to significant deviations from the original business case. Furthermore, it highlights a breakdown in the PRINCE2 principle of “Defined Roles and Responsibilities,” as the Project Board is not fulfilling its oversight role effectively and is instead micromanaging operational aspects, which should primarily be the responsibility of the Project Manager. The correct approach, as per PRINCE2, would involve the Project Manager escalating these deviations to the Project Board, clearly articulating the impact on the business case and tolerances, and seeking a formal decision on scope changes through the established Change Control Procedure. The Project Board’s actions, as described, indicate a failure to adhere to the defined governance structure and the principles of controlled scope management.
-
Question 18 of 30
18. Question
A software development project, initiated to streamline internal logistics, is encountering persistent pressure from various departments to incorporate new functionalities that were not part of the original scope. The Project Manager is concerned about the project’s trajectory, as these requests are frequently presented as urgent operational necessities, often with limited impact analysis provided. The project board is focused on rapid deployment, and the Project Manager feels constrained in pushing back on these additions without jeopardizing stakeholder relationships and the perceived pace of delivery. Which PRINCE2 theme, when rigorously applied, offers the most direct mechanism for controlling these evolving requirements and ensuring continued alignment with the business case?
Correct
The scenario describes a project experiencing significant scope creep due to evolving market demands and a lack of rigorous change control. The Project Manager is facing pressure to deliver quickly, leading to potential compromises on quality and adherence to the original business case. The PRINCE2 principles of ‘continued business justification’ and ‘manage by exception’ are being challenged. The ‘manage by stages’ principle is also relevant as the project is not clearly defining what constitutes a completed stage.
The most appropriate PRINCE2 theme to address this situation is Change, as it directly deals with identifying, assessing, and controlling changes to the project’s baseline. The Change theme outlines the processes for managing requests for change, ensuring they are evaluated against the business case and project objectives before being approved or rejected. Implementing a robust change control approach within the Change theme would involve establishing a Change Authority, using a Change Request form, and conducting impact assessments for each proposed modification. This would help to prevent uncontrolled scope creep, maintain focus on the business case, and ensure that any changes are properly justified and resourced.
While Risk management is important for identifying potential threats, it is a reactive measure to existing or potential issues, whereas Change management is proactive in controlling modifications. Quality management focuses on ensuring the project meets its quality criteria, but it doesn’t directly address the *initiation* and *approval* of changes that might impact quality. Project Product Management ensures the correct product is delivered, but it doesn’t provide the framework for managing the *evolution* of that product through controlled changes. Therefore, the Change theme is the most fundamental and directly applicable theme to address the core problem of uncontrolled scope creep and evolving requirements.
Incorrect
The scenario describes a project experiencing significant scope creep due to evolving market demands and a lack of rigorous change control. The Project Manager is facing pressure to deliver quickly, leading to potential compromises on quality and adherence to the original business case. The PRINCE2 principles of ‘continued business justification’ and ‘manage by exception’ are being challenged. The ‘manage by stages’ principle is also relevant as the project is not clearly defining what constitutes a completed stage.
The most appropriate PRINCE2 theme to address this situation is Change, as it directly deals with identifying, assessing, and controlling changes to the project’s baseline. The Change theme outlines the processes for managing requests for change, ensuring they are evaluated against the business case and project objectives before being approved or rejected. Implementing a robust change control approach within the Change theme would involve establishing a Change Authority, using a Change Request form, and conducting impact assessments for each proposed modification. This would help to prevent uncontrolled scope creep, maintain focus on the business case, and ensure that any changes are properly justified and resourced.
While Risk management is important for identifying potential threats, it is a reactive measure to existing or potential issues, whereas Change management is proactive in controlling modifications. Quality management focuses on ensuring the project meets its quality criteria, but it doesn’t directly address the *initiation* and *approval* of changes that might impact quality. Project Product Management ensures the correct product is delivered, but it doesn’t provide the framework for managing the *evolution* of that product through controlled changes. Therefore, the Change theme is the most fundamental and directly applicable theme to address the core problem of uncontrolled scope creep and evolving requirements.
-
Question 19 of 30
19. Question
A critical regulatory change has been enacted, directly impacting the core assumptions underpinning the business case for a large-scale infrastructure development project. The project manager, after identifying the significant threat to the project’s viability and informing the Project Board, needs to determine the next PRINCE2-aligned course of action. The Project Board has acknowledged the report and is convening an urgent meeting to discuss the implications. Which of the following actions by the Project Board would be the most appropriate next step to ensure the project remains aligned with business objectives or is appropriately terminated?
Correct
The scenario describes a project facing significant external shifts impacting its core assumptions and objectives. The PRINCE2 Practitioner’s role in such a situation is to re-evaluate the project’s viability and strategic alignment. The project board has been informed of the emerging risks and the need for a fundamental review. The question asks for the most appropriate PRINCE2 action to take next.
In PRINCE2, when a project’s viability is significantly threatened by external factors, the project manager must escalate this to the Project Board. The Project Board is responsible for the project’s overall direction and has the authority to approve changes to the project’s objectives or even terminate it. The ‘Initiate a Project’ process is about setting up the project, and while it involves defining the project mandate and initial business case, it’s not the immediate response to a crisis that has already occurred. The ‘Manage by Exception’ principle dictates that the Project Board only gets involved when tolerances are forecast to be exceeded. This situation clearly indicates that tolerances are being threatened, and potentially the entire business case.
The ‘Control a Stage’ process focuses on day-to-day management within a stage, and while it includes reporting, it doesn’t inherently cover the strategic re-evaluation required here. The ‘Close a Project’ process is for when the project is completed or terminated, which is a potential outcome but not the immediate next step in assessing the situation. The most critical action is to formally present the updated situation and the implications for the business case to the Project Board for a decision. This is typically achieved through an Exception Report, which triggers the Project Board to review the project’s direction. If the Project Board decides to continue, they would likely authorize a new initiation stage or a revised initiation stage to re-establish the project’s foundation based on the new circumstances. Therefore, the next logical step is for the Project Board to receive and act upon the Exception Report, which would lead to a decision on how to proceed, potentially including a revised initiation or a new project. The PRINCE2 principle of ‘Focus on Products’ is always relevant, but the immediate need is strategic direction. ‘Manage by Stages’ is about breaking down the project, but the current issue transcends stage boundaries. ‘Tailor PRINCE2’ is about adapting the method, but the core decision-making authority remains with the Project Board.
Given the options, the most direct and correct PRINCE2 action following the identification of a significant threat to the business case, and after informing the Project Board, is for the Project Board to decide on the project’s future. This decision would typically involve authorizing the Project Manager to undertake activities to revise the project’s direction, which could manifest as a new initiation stage or a revised initiation stage. The key is the Project Board’s decision to re-establish the project’s mandate and business case.
Incorrect
The scenario describes a project facing significant external shifts impacting its core assumptions and objectives. The PRINCE2 Practitioner’s role in such a situation is to re-evaluate the project’s viability and strategic alignment. The project board has been informed of the emerging risks and the need for a fundamental review. The question asks for the most appropriate PRINCE2 action to take next.
In PRINCE2, when a project’s viability is significantly threatened by external factors, the project manager must escalate this to the Project Board. The Project Board is responsible for the project’s overall direction and has the authority to approve changes to the project’s objectives or even terminate it. The ‘Initiate a Project’ process is about setting up the project, and while it involves defining the project mandate and initial business case, it’s not the immediate response to a crisis that has already occurred. The ‘Manage by Exception’ principle dictates that the Project Board only gets involved when tolerances are forecast to be exceeded. This situation clearly indicates that tolerances are being threatened, and potentially the entire business case.
The ‘Control a Stage’ process focuses on day-to-day management within a stage, and while it includes reporting, it doesn’t inherently cover the strategic re-evaluation required here. The ‘Close a Project’ process is for when the project is completed or terminated, which is a potential outcome but not the immediate next step in assessing the situation. The most critical action is to formally present the updated situation and the implications for the business case to the Project Board for a decision. This is typically achieved through an Exception Report, which triggers the Project Board to review the project’s direction. If the Project Board decides to continue, they would likely authorize a new initiation stage or a revised initiation stage to re-establish the project’s foundation based on the new circumstances. Therefore, the next logical step is for the Project Board to receive and act upon the Exception Report, which would lead to a decision on how to proceed, potentially including a revised initiation or a new project. The PRINCE2 principle of ‘Focus on Products’ is always relevant, but the immediate need is strategic direction. ‘Manage by Stages’ is about breaking down the project, but the current issue transcends stage boundaries. ‘Tailor PRINCE2’ is about adapting the method, but the core decision-making authority remains with the Project Board.
Given the options, the most direct and correct PRINCE2 action following the identification of a significant threat to the business case, and after informing the Project Board, is for the Project Board to decide on the project’s future. This decision would typically involve authorizing the Project Manager to undertake activities to revise the project’s direction, which could manifest as a new initiation stage or a revised initiation stage. The key is the Project Board’s decision to re-establish the project’s mandate and business case.
-
Question 20 of 30
20. Question
Anya, a seasoned project manager, is steering a critical digital transformation initiative employing the PRINCE2 methodology. Midway through the execution stage, the primary third-party provider of a core integration middleware announces its immediate deprecation, rendering the existing architecture unsustainable. This development introduces significant uncertainty regarding the project’s ability to deliver its intended benefits within the established time and cost constraints. Anya has meticulously documented the impact, identifying several potential technical workarounds and a revised timeline, but the scale of the disruption is projected to exceed her delegated authority for managing deviations. Which of the following actions should Anya prioritize as her immediate next step to adhere to PRINCE2 governance?
Correct
The scenario describes a project manager, Anya, who is leading a complex software development project using PRINCE2. The project faces a significant challenge: a key technology component, crucial for the system’s integration, has been unexpectedly deprecated by its vendor, requiring a substantial redesign. This situation directly impacts the project’s scope, timeline, and potentially its budget. Anya needs to address this emergent risk.
According to PRINCE2 principles and themes, particularly the ‘Managing by Exception’ principle and the ‘Risk’ theme, the project manager’s primary responsibility is to manage the project on a day-to-day basis and escalate issues that exceed defined tolerances. The Project Board is responsible for providing overall direction and making strategic decisions, especially when project parameters are significantly threatened.
In this situation, the deprecation of the technology component represents a major deviation from the baseline plan, likely exceeding the Project Manager’s delegated tolerances for scope, time, or cost. Therefore, Anya’s immediate and correct action, as per PRINCE2, is to inform the Project Board and present them with options for how to proceed. This allows the Project Board to make an informed decision about the project’s future, such as authorizing a change request to redesign the component, re-scoping the project, or even terminating it if the impact is too severe.
Option (a) is correct because it aligns with the PRINCE2 approach to managing exceptions and involving the Project Board in significant decisions that impact project objectives. Options (b), (c), and (d) are incorrect because they represent actions that either bypass the Project Board, fail to address the root cause effectively, or are not the primary PRINCE2-prescribed first step for such a significant issue. Specifically, continuing without informing the board violates the ‘Managing by Exception’ principle. Simply adjusting the plan without formal approval for such a substantial change would be a breach of delegated authority. Focusing solely on technical solutions without considering the business case and stakeholder impact, as implied by only looking for alternative technical components, is incomplete without Project Board oversight.
Incorrect
The scenario describes a project manager, Anya, who is leading a complex software development project using PRINCE2. The project faces a significant challenge: a key technology component, crucial for the system’s integration, has been unexpectedly deprecated by its vendor, requiring a substantial redesign. This situation directly impacts the project’s scope, timeline, and potentially its budget. Anya needs to address this emergent risk.
According to PRINCE2 principles and themes, particularly the ‘Managing by Exception’ principle and the ‘Risk’ theme, the project manager’s primary responsibility is to manage the project on a day-to-day basis and escalate issues that exceed defined tolerances. The Project Board is responsible for providing overall direction and making strategic decisions, especially when project parameters are significantly threatened.
In this situation, the deprecation of the technology component represents a major deviation from the baseline plan, likely exceeding the Project Manager’s delegated tolerances for scope, time, or cost. Therefore, Anya’s immediate and correct action, as per PRINCE2, is to inform the Project Board and present them with options for how to proceed. This allows the Project Board to make an informed decision about the project’s future, such as authorizing a change request to redesign the component, re-scoping the project, or even terminating it if the impact is too severe.
Option (a) is correct because it aligns with the PRINCE2 approach to managing exceptions and involving the Project Board in significant decisions that impact project objectives. Options (b), (c), and (d) are incorrect because they represent actions that either bypass the Project Board, fail to address the root cause effectively, or are not the primary PRINCE2-prescribed first step for such a significant issue. Specifically, continuing without informing the board violates the ‘Managing by Exception’ principle. Simply adjusting the plan without formal approval for such a substantial change would be a breach of delegated authority. Focusing solely on technical solutions without considering the business case and stakeholder impact, as implied by only looking for alternative technical components, is incomplete without Project Board oversight.
-
Question 21 of 30
21. Question
Consider a scenario where the ‘Aurora’ project, aimed at enhancing customer relationship management software, is midway through its execution. A newly enacted government regulation mandates that all customer data must be encrypted using a specific, previously undisclosed algorithm by the end of the fiscal year. This requirement fundamentally alters the technical approach for data storage and retrieval, significantly increasing development effort, required expertise, and project duration, and potentially impacting the original business case. What is the most appropriate PRINCE2-compliant action for the Project Manager to take in this situation?
Correct
The question assesses understanding of how to handle a significant change in project direction that impacts scope, resources, and timeline, and how this aligns with PRINCE2 principles and processes. The scenario describes a mandatory regulatory change requiring a substantial alteration to the project’s technical solution and its integration with existing systems. This necessitates a formal approach to managing the change, involving re-evaluation of the project’s viability and alignment with business objectives.
In PRINCE2, the process for handling such a significant change is through the ‘Manage a Stage Boundary’ process, which includes creating an Exception Plan if the current plan is no longer valid, and then seeking approval from the Project Board. The Project Board’s role is to decide whether to continue the project, with or without modifications, or to terminate it. Given the mandatory nature of the regulatory change and its substantial impact, the Project Board must be informed and involved in making a decision about the project’s future. The Project Manager cannot unilaterally decide to proceed with a significantly altered scope and budget without board approval. Therefore, the most appropriate immediate action is to inform the Project Board and seek their guidance and decision on how to proceed, which could involve revising the project plan or initiating a new project. This aligns with the PRINCE2 principle of ‘Continued Business Justification’ and the management role of the Project Board.
Incorrect
The question assesses understanding of how to handle a significant change in project direction that impacts scope, resources, and timeline, and how this aligns with PRINCE2 principles and processes. The scenario describes a mandatory regulatory change requiring a substantial alteration to the project’s technical solution and its integration with existing systems. This necessitates a formal approach to managing the change, involving re-evaluation of the project’s viability and alignment with business objectives.
In PRINCE2, the process for handling such a significant change is through the ‘Manage a Stage Boundary’ process, which includes creating an Exception Plan if the current plan is no longer valid, and then seeking approval from the Project Board. The Project Board’s role is to decide whether to continue the project, with or without modifications, or to terminate it. Given the mandatory nature of the regulatory change and its substantial impact, the Project Board must be informed and involved in making a decision about the project’s future. The Project Manager cannot unilaterally decide to proceed with a significantly altered scope and budget without board approval. Therefore, the most appropriate immediate action is to inform the Project Board and seek their guidance and decision on how to proceed, which could involve revising the project plan or initiating a new project. This aligns with the PRINCE2 principle of ‘Continued Business Justification’ and the management role of the Project Board.
-
Question 22 of 30
22. Question
A complex transformation project, initiated with clearly defined objectives and a robust business case, is now facing substantial pressure from a newly formed steering committee representing key operational departments. This committee has presented a series of emergent requirements that, if incorporated, would significantly expand the project’s scope beyond the agreed tolerances for time and cost. The Project Manager has been diligently assessing these requests, but it’s clear that the cumulative impact will breach the established limits. The Project Board has requested an update on the project’s status and a proposal for managing these new demands. What is the most appropriate immediate next step for the Project Manager, adhering strictly to PRINCE2 principles and processes, to ensure appropriate governance and control?
Correct
The scenario describes a project experiencing significant scope creep due to emergent stakeholder requirements that were not initially identified during the initiation phase. The project board has requested a revised baseline, but the Project Manager is hesitant to formally incorporate all new requests without a thorough assessment. In PRINCE2, the ‘Manage by Exception’ principle dictates that the Project Board only needs to be informed when a project is forecast to deviate from its agreed tolerances. The Project Manager’s primary responsibility is to manage the project within these tolerances. When new requirements emerge that threaten to exceed agreed tolerances for scope, time, or cost, the Project Manager must raise an Exception Report. This report details the deviation, its impact, and recommended corrective actions. The Project Board then decides how to proceed, which might include approving a revised baseline or directing the Project Manager to manage the deviation. The question asks for the *next* step the Project Manager should take to address the situation where the project is forecast to exceed tolerances. Option D, raising an Exception Report to the Project Board, is the direct consequence of forecasting a deviation from agreed tolerances and is the mechanism by which the Project Board is informed and can make decisions. Options A, B, and C are either premature (A – formal approval before assessment), incorrect in PRINCE2 terminology (B – ‘Change Request Log’ is a tool, not the action itself), or not the most immediate and appropriate PRINCE2 response to a forecast tolerance breach (C – ‘escalating to the Project Assurance role’ might happen as part of the process but the direct PRINCE2 action for a tolerance breach is the Exception Report). Therefore, the most accurate and immediate PRINCE2 action is to formally report the forecast deviation.
Incorrect
The scenario describes a project experiencing significant scope creep due to emergent stakeholder requirements that were not initially identified during the initiation phase. The project board has requested a revised baseline, but the Project Manager is hesitant to formally incorporate all new requests without a thorough assessment. In PRINCE2, the ‘Manage by Exception’ principle dictates that the Project Board only needs to be informed when a project is forecast to deviate from its agreed tolerances. The Project Manager’s primary responsibility is to manage the project within these tolerances. When new requirements emerge that threaten to exceed agreed tolerances for scope, time, or cost, the Project Manager must raise an Exception Report. This report details the deviation, its impact, and recommended corrective actions. The Project Board then decides how to proceed, which might include approving a revised baseline or directing the Project Manager to manage the deviation. The question asks for the *next* step the Project Manager should take to address the situation where the project is forecast to exceed tolerances. Option D, raising an Exception Report to the Project Board, is the direct consequence of forecasting a deviation from agreed tolerances and is the mechanism by which the Project Board is informed and can make decisions. Options A, B, and C are either premature (A – formal approval before assessment), incorrect in PRINCE2 terminology (B – ‘Change Request Log’ is a tool, not the action itself), or not the most immediate and appropriate PRINCE2 response to a forecast tolerance breach (C – ‘escalating to the Project Assurance role’ might happen as part of the process but the direct PRINCE2 action for a tolerance breach is the Exception Report). Therefore, the most accurate and immediate PRINCE2 action is to formally report the forecast deviation.
-
Question 23 of 30
23. Question
Consider a scenario where a project, initiated using the PRINCE2 methodology, is operating within a sector experiencing rapid technological disruption and evolving compliance mandates. The project’s initial scope and timelines, established during the ‘Initiating a Project’ process, are now being significantly challenged by these external factors. The Project Board has requested the Project Manager to outline the most effective approach to maintain project control and business relevance without resorting to a complete re-initiation. Which of the following actions best reflects the application of PRINCE2 principles and themes in this context?
Correct
The PRINCE2 methodology emphasizes a pragmatic approach to project management, focusing on business justification, defined roles and responsibilities, management by stages, and management by exception. The question probes the understanding of how PRINCE2 principles are applied in dynamic environments. The core of PRINCE2’s adaptability lies in its principles and themes, which provide a framework that can be tailored. Specifically, the principle of ‘Manage by Exception’ is crucial for handling deviations from the plan, allowing for proactive intervention without constant micromanagement. The ‘Themes’ provide guidance on how to manage aspects of the project, such as Risk, Quality, and Change, which are all critical in volatile situations. The ‘Processes’ outline the steps to be taken, but their application can be adapted.
In this scenario, the project team is facing shifting market demands and an evolving regulatory landscape. This requires a project management approach that can readily incorporate changes and maintain focus on the business case. The PRINCE2 principle of ‘Focus on Products’ ensures that the project delivers tangible outputs that meet defined requirements, which can be reassessed as the environment changes. The ‘Manage by Stages’ principle allows for periodic review and re-planning, providing natural checkpoints to adapt to new information. The ‘Tailor to suit the project environment’ principle is paramount, recognizing that a rigid application is often counterproductive. Therefore, a project manager adept at applying PRINCE2 would leverage the inherent flexibility of the methodology, particularly by refining the stage plans and risk responses based on the new information, rather than discarding the entire framework. The ability to pivot strategies is directly supported by the iterative nature of PRINCE2 and the emphasis on continuous business justification.
Incorrect
The PRINCE2 methodology emphasizes a pragmatic approach to project management, focusing on business justification, defined roles and responsibilities, management by stages, and management by exception. The question probes the understanding of how PRINCE2 principles are applied in dynamic environments. The core of PRINCE2’s adaptability lies in its principles and themes, which provide a framework that can be tailored. Specifically, the principle of ‘Manage by Exception’ is crucial for handling deviations from the plan, allowing for proactive intervention without constant micromanagement. The ‘Themes’ provide guidance on how to manage aspects of the project, such as Risk, Quality, and Change, which are all critical in volatile situations. The ‘Processes’ outline the steps to be taken, but their application can be adapted.
In this scenario, the project team is facing shifting market demands and an evolving regulatory landscape. This requires a project management approach that can readily incorporate changes and maintain focus on the business case. The PRINCE2 principle of ‘Focus on Products’ ensures that the project delivers tangible outputs that meet defined requirements, which can be reassessed as the environment changes. The ‘Manage by Stages’ principle allows for periodic review and re-planning, providing natural checkpoints to adapt to new information. The ‘Tailor to suit the project environment’ principle is paramount, recognizing that a rigid application is often counterproductive. Therefore, a project manager adept at applying PRINCE2 would leverage the inherent flexibility of the methodology, particularly by refining the stage plans and risk responses based on the new information, rather than discarding the entire framework. The ability to pivot strategies is directly supported by the iterative nature of PRINCE2 and the emphasis on continuous business justification.
-
Question 24 of 30
24. Question
A PRINCE2 project, tasked with developing a novel quantum encryption algorithm, is nearing the end of its current stage. The Project Manager has diligently managed the project within the approved stage tolerances. However, an unforeseen technical breakthrough in a related field has presented an opportunity to significantly enhance the algorithm’s security, but this will require an additional three weeks of development and an extra \(£15,000\) in specialized computing resources. The Project Manager has already utilized the entire management reserve allocated for this stage. The Project Board has delegated authority for stage tolerances but has not authorized them to approve changes that would exceed the overall project tolerance for time or cost. Given this situation, what is the most appropriate next step for the Project Board after reviewing the Project Manager’s Exception Report detailing these circumstances?
Correct
The core of this question lies in understanding the PRINCE2 approach to managing exceptions and the role of the Project Board in decision-making. When a project exceeds its approved tolerance for time, and the Project Manager has already utilized the management reserve within the current stage, the Project Manager’s next step is to raise an Exception Report. This report details the deviation, its impact, and proposed corrective actions. The Project Board then reviews this report. If the proposed actions are within the Board’s delegated authority and tolerances, they can approve them. However, if the deviation requires more time or resources that exceed the Board’s delegated authority or the project’s overall tolerances, the Project Board must escalate the situation. In PRINCE2, this escalation typically involves requesting a Project Initiation Documentation (PID) revision or a new Project Brief from the Project Sponsor or relevant corporate authority. The Project Board itself does not have the authority to re-baseline the project or authorize expenditure beyond its delegated limits. Therefore, the most appropriate action for the Project Board, after receiving an Exception Report indicating a significant deviation beyond their delegated authority, is to seek approval for a revised project plan or a change to the project’s constraints from a higher authority, such as the Project Sponsor or the governing body.
Incorrect
The core of this question lies in understanding the PRINCE2 approach to managing exceptions and the role of the Project Board in decision-making. When a project exceeds its approved tolerance for time, and the Project Manager has already utilized the management reserve within the current stage, the Project Manager’s next step is to raise an Exception Report. This report details the deviation, its impact, and proposed corrective actions. The Project Board then reviews this report. If the proposed actions are within the Board’s delegated authority and tolerances, they can approve them. However, if the deviation requires more time or resources that exceed the Board’s delegated authority or the project’s overall tolerances, the Project Board must escalate the situation. In PRINCE2, this escalation typically involves requesting a Project Initiation Documentation (PID) revision or a new Project Brief from the Project Sponsor or relevant corporate authority. The Project Board itself does not have the authority to re-baseline the project or authorize expenditure beyond its delegated limits. Therefore, the most appropriate action for the Project Board, after receiving an Exception Report indicating a significant deviation beyond their delegated authority, is to seek approval for a revised project plan or a change to the project’s constraints from a higher authority, such as the Project Sponsor or the governing body.
-
Question 25 of 30
25. Question
A project delivering a new integrated supply chain management system is progressing, and the Project Manager has just received the latest status update for a critical Work Package focused on system integration testing. The update indicates that due to unforeseen complexities in legacy system interfacing, the Work Package is now forecast to exceed its allocated budget tolerance by 15%. The Project Manager has explored immediate mitigation options within their delegated authority but has been unable to bring the forecast back within tolerance. Considering the PRINCE2 principles, what is the most appropriate immediate action for the Project Manager to take?
Correct
The question focuses on the PRINCE2 principle of ‘Manage by Exception’. This principle states that management attention should be concentrated on areas where performance deviates outside acceptable tolerances. When a project board receives a Highlight Report indicating that a specific Work Package is forecast to exceed its agreed tolerance for ‘Cost’, and no immediate corrective action is planned or feasible within the Project Manager’s delegated authority, the Project Manager must escalate this issue. Escalation is typically done via an Exception Report to the Project Board. The Exception Report details the deviation, its impact, and proposed options for resolution, including a revised plan. The Project Board then reviews this report and decides on the appropriate course of action, which might involve approving a revised tolerance, authorizing additional resources, or directing a change in approach. Therefore, the most appropriate next step for the Project Manager, having identified a potential cost overrun beyond their authority, is to prepare and submit an Exception Report. This demonstrates proactive management and adherence to the ‘Manage by Exception’ principle by highlighting a deviation and seeking guidance and approval for a solution.
Incorrect
The question focuses on the PRINCE2 principle of ‘Manage by Exception’. This principle states that management attention should be concentrated on areas where performance deviates outside acceptable tolerances. When a project board receives a Highlight Report indicating that a specific Work Package is forecast to exceed its agreed tolerance for ‘Cost’, and no immediate corrective action is planned or feasible within the Project Manager’s delegated authority, the Project Manager must escalate this issue. Escalation is typically done via an Exception Report to the Project Board. The Exception Report details the deviation, its impact, and proposed options for resolution, including a revised plan. The Project Board then reviews this report and decides on the appropriate course of action, which might involve approving a revised tolerance, authorizing additional resources, or directing a change in approach. Therefore, the most appropriate next step for the Project Manager, having identified a potential cost overrun beyond their authority, is to prepare and submit an Exception Report. This demonstrates proactive management and adherence to the ‘Manage by Exception’ principle by highlighting a deviation and seeking guidance and approval for a solution.
-
Question 26 of 30
26. Question
Elara, a project manager leading a complex software development initiative, is facing escalating pressure from a key stakeholder for substantial feature additions that were not part of the original approved scope. These requests stem from newly identified market opportunities that have emerged since the project’s inception. Elara recognizes that incorporating these changes would significantly alter the project’s timeline, budget, and potentially its core objectives. Considering the PRINCE2 principles, what is the most critical element Elara must ensure is demonstrably valid before proceeding with or recommending any significant adaptation to the project’s trajectory?
Correct
The scenario describes a situation where a project is experiencing significant scope creep due to evolving market demands and the client’s desire to incorporate new features. The project manager, Elara, needs to decide how to handle this. In PRINCE2, the **Initiating a Project** process defines the need for a Project Brief, which includes the Project Product Description and the Project Approach. The **Controlling a Stage** process and the **Managing Product Delivery** process are concerned with executing the work and managing deviations within a stage. The **Managing a Stage Boundary** process is specifically for reviewing progress at the end of a stage and planning the next. However, the most appropriate PRINCE2 principle to address significant scope changes that fundamentally alter the project’s viability or objectives is **Continued Business Justification**. If the new requirements mean the original business case is no longer valid, or if the cost/benefit analysis shifts dramatically, the project may need to be re-evaluated or even terminated. While other aspects of PRINCE2 (like change control, managing scope, and stakeholder engagement) are involved in handling scope creep, the overarching principle that governs whether the project should continue in its altered form is the continued business justification. Therefore, ensuring this remains valid is paramount. The question asks what is most important to ensure, implying a foundational PRINCE2 principle. The ability to adapt and pivot strategies when needed, as mentioned in the behavioral competencies, is crucial, but it’s the *why* behind the pivot that PRINCE2 emphasizes. If the pivot is driven by a change that invalidates the business case, then continued business justification becomes the most critical aspect. The project board’s role in approving major changes is also key, but this stems from the need to maintain business justification. The question focuses on the *project manager’s* most important consideration in this context. While managing scope and stakeholder expectations are vital actions, the underlying principle that dictates the project’s continued existence in the face of such changes is continued business justification.
Incorrect
The scenario describes a situation where a project is experiencing significant scope creep due to evolving market demands and the client’s desire to incorporate new features. The project manager, Elara, needs to decide how to handle this. In PRINCE2, the **Initiating a Project** process defines the need for a Project Brief, which includes the Project Product Description and the Project Approach. The **Controlling a Stage** process and the **Managing Product Delivery** process are concerned with executing the work and managing deviations within a stage. The **Managing a Stage Boundary** process is specifically for reviewing progress at the end of a stage and planning the next. However, the most appropriate PRINCE2 principle to address significant scope changes that fundamentally alter the project’s viability or objectives is **Continued Business Justification**. If the new requirements mean the original business case is no longer valid, or if the cost/benefit analysis shifts dramatically, the project may need to be re-evaluated or even terminated. While other aspects of PRINCE2 (like change control, managing scope, and stakeholder engagement) are involved in handling scope creep, the overarching principle that governs whether the project should continue in its altered form is the continued business justification. Therefore, ensuring this remains valid is paramount. The question asks what is most important to ensure, implying a foundational PRINCE2 principle. The ability to adapt and pivot strategies when needed, as mentioned in the behavioral competencies, is crucial, but it’s the *why* behind the pivot that PRINCE2 emphasizes. If the pivot is driven by a change that invalidates the business case, then continued business justification becomes the most critical aspect. The project board’s role in approving major changes is also key, but this stems from the need to maintain business justification. The question focuses on the *project manager’s* most important consideration in this context. While managing scope and stakeholder expectations are vital actions, the underlying principle that dictates the project’s continued existence in the face of such changes is continued business justification.
-
Question 27 of 30
27. Question
A Project Manager is overseeing the ‘Phoenix’ project, which is tasked with developing a novel renewable energy storage system. The Project Board has established strict tolerances for schedule adherence, with a maximum allowable slip of 5% of the total project duration. During the execution phase, the Project Manager discovers that a critical sub-assembly development, currently on the critical path, is experiencing unforeseen technical challenges that will likely cause a delay of 7% of the total project duration. The Project Manager has already explored internal mitigation options, such as re-prioritizing other project tasks and attempting to leverage existing team expertise, but these are insufficient to bring the sub-assembly back within the original tolerance. What is the most appropriate next course of action for the Project Manager in adherence to PRINCE2 principles?
Correct
The PRINCE2 methodology emphasizes the importance of managing by exception. This principle dictates that a project manager should only escalate issues to the Project Board when tolerances are forecast to be exceeded. The Project Board then has the authority to make decisions on how to proceed. In this scenario, the Project Board has provided clear guidance and agreed tolerances for the project. When the Project Manager identifies that a specific activity is likely to exceed its allocated time tolerance, the immediate action is not to make a unilateral decision to extend the deadline or reallocate resources without authorization. Instead, the Project Manager must inform the Project Board of the potential exception. This is done through an Exception Report. The Exception Report details the deviation from the plan, the impact of this deviation, and proposed options for the Project Board to consider. The Project Board then reviews the report and decides on the appropriate course of action, which could include approving an extension, reallocating resources, or adjusting the scope. Therefore, the most appropriate next step for the Project Manager, after identifying the potential time tolerance breach, is to prepare and submit an Exception Report to the Project Board. This aligns with the PRINCE2 principle of managing by exception and the governance structure of PRINCE2 projects.
Incorrect
The PRINCE2 methodology emphasizes the importance of managing by exception. This principle dictates that a project manager should only escalate issues to the Project Board when tolerances are forecast to be exceeded. The Project Board then has the authority to make decisions on how to proceed. In this scenario, the Project Board has provided clear guidance and agreed tolerances for the project. When the Project Manager identifies that a specific activity is likely to exceed its allocated time tolerance, the immediate action is not to make a unilateral decision to extend the deadline or reallocate resources without authorization. Instead, the Project Manager must inform the Project Board of the potential exception. This is done through an Exception Report. The Exception Report details the deviation from the plan, the impact of this deviation, and proposed options for the Project Board to consider. The Project Board then reviews the report and decides on the appropriate course of action, which could include approving an extension, reallocating resources, or adjusting the scope. Therefore, the most appropriate next step for the Project Manager, after identifying the potential time tolerance breach, is to prepare and submit an Exception Report to the Project Board. This aligns with the PRINCE2 principle of managing by exception and the governance structure of PRINCE2 projects.
-
Question 28 of 30
28. Question
A critical supplier for the ‘Aurora’ project, vital for delivering the next major milestone, has unexpectedly declared bankruptcy, significantly impacting the project’s delivery timeline and budget. The deviation from the planned timeline tolerance is estimated to be 15%, and the budget tolerance is projected to be exceeded by 10%. As the Project Manager, what is the immediate and most appropriate action to take according to PRINCE2 principles?
Correct
The question assesses understanding of PRINCE2’s emphasis on managing by exception and the role of tolerances. When a project experiences a deviation that exceeds a defined tolerance, the Project Manager is obligated to escalate the issue to the next higher authority, which in this scenario is the Project Board. The Project Board then has the responsibility to decide on the appropriate course of action, which could involve revising the plan, reallocating resources, or accepting the deviation. The Project Manager’s role is to provide the necessary information for this decision, not to unilaterally make it or wait for further instructions without informing the Project Board. Option b is incorrect because while the Project Manager should try to resolve issues within their delegated authority, exceeding tolerances mandates escalation. Option c is incorrect as the Project Board, not the Project Assurance, is the primary decision-making body for exceptions that breach tolerances. Option d is incorrect because the Project Manager’s responsibility is to report and seek direction, not to independently adjust project tolerances without formal approval, especially when they have been breached.
Incorrect
The question assesses understanding of PRINCE2’s emphasis on managing by exception and the role of tolerances. When a project experiences a deviation that exceeds a defined tolerance, the Project Manager is obligated to escalate the issue to the next higher authority, which in this scenario is the Project Board. The Project Board then has the responsibility to decide on the appropriate course of action, which could involve revising the plan, reallocating resources, or accepting the deviation. The Project Manager’s role is to provide the necessary information for this decision, not to unilaterally make it or wait for further instructions without informing the Project Board. Option b is incorrect because while the Project Manager should try to resolve issues within their delegated authority, exceeding tolerances mandates escalation. Option c is incorrect as the Project Board, not the Project Assurance, is the primary decision-making body for exceptions that breach tolerances. Option d is incorrect because the Project Manager’s responsibility is to report and seek direction, not to independently adjust project tolerances without formal approval, especially when they have been breached.
-
Question 29 of 30
29. Question
Consider a situation where the Project Manager for the ‘Aurora’ initiative, an ambitious digital transformation program, has identified a critical risk. This risk, if it materializes, is projected to cause the project to exceed its approved budget tolerance by 15% and, concurrently, deliver a key functionality that the primary customer has now deemed a low priority due to recent market shifts. Which PRINCE2 management action should the Project Manager initiate as the immediate next step to address this forecast deviation from the Business Case?
Correct
The question probes the understanding of PRINCE2’s approach to managing change, specifically concerning the Business Case and the appropriate PRINCE2 roles and processes involved when a significant deviation from the approved Business Case occurs.
A deviation from the Business Case, especially one that impacts the project’s viability or objectives, requires careful consideration within the PRINCE2 framework. The PRINCE2 manual emphasizes that the Business Case is the primary justification for the project and must be kept up-to-date. If a project is forecast to deviate from its Business Case, it must be escalated.
The Project Board is ultimately responsible for the project’s success and must be informed of such deviations. They have the authority to decide whether to continue the project, modify it, or terminate it. The Project Manager’s role is to monitor the project against the Business Case and report any significant deviations.
In this scenario, the Project Manager has identified a significant risk that, if realized, will cause the project to exceed its approved budget by 15% and deliver a feature that is no longer considered a priority by the customer. This constitutes a major threat to the Business Case.
The PRINCE2 process for managing issues and risks, “Manage by Exception,” dictates that the Project Manager should raise an Exception Report when a project is forecast to exceed tolerances. This Exception Report is then escalated to the Project Board. The Project Board will then review the Exception Report, assess the impact on the Business Case, and decide on the appropriate course of action. This might involve authorizing additional funds, changing the scope, or even terminating the project.
Therefore, the most appropriate PRINCE2 action is for the Project Manager to create an Exception Report and present it to the Project Board for a decision. The Project Board will then review the Business Case, the impact of the deviation, and potentially request a revised Business Case or authorize changes.
Incorrect
The question probes the understanding of PRINCE2’s approach to managing change, specifically concerning the Business Case and the appropriate PRINCE2 roles and processes involved when a significant deviation from the approved Business Case occurs.
A deviation from the Business Case, especially one that impacts the project’s viability or objectives, requires careful consideration within the PRINCE2 framework. The PRINCE2 manual emphasizes that the Business Case is the primary justification for the project and must be kept up-to-date. If a project is forecast to deviate from its Business Case, it must be escalated.
The Project Board is ultimately responsible for the project’s success and must be informed of such deviations. They have the authority to decide whether to continue the project, modify it, or terminate it. The Project Manager’s role is to monitor the project against the Business Case and report any significant deviations.
In this scenario, the Project Manager has identified a significant risk that, if realized, will cause the project to exceed its approved budget by 15% and deliver a feature that is no longer considered a priority by the customer. This constitutes a major threat to the Business Case.
The PRINCE2 process for managing issues and risks, “Manage by Exception,” dictates that the Project Manager should raise an Exception Report when a project is forecast to exceed tolerances. This Exception Report is then escalated to the Project Board. The Project Board will then review the Exception Report, assess the impact on the Business Case, and decide on the appropriate course of action. This might involve authorizing additional funds, changing the scope, or even terminating the project.
Therefore, the most appropriate PRINCE2 action is for the Project Manager to create an Exception Report and present it to the Project Board for a decision. The Project Board will then review the Business Case, the impact of the deviation, and potentially request a revised Business Case or authorize changes.
-
Question 30 of 30
30. Question
During the execution of the ‘Develop Solutions’ stage for the ‘Aether Project’, the Project Manager forecasts that the estimated final cost will exceed the approved budget tolerance by 8%. The Project Board has previously established that any forecast deviation exceeding 5% of the budget tolerance requires their immediate attention and decision. Considering the PRINCE2 principle of ‘managing by exception’, what is the most appropriate immediate action for the Project Manager and the Project Board respectively?
Correct
The question assesses understanding of PRINCE2’s emphasis on the ‘managing by exception’ principle and its implications for the Project Board’s oversight. The Project Board delegates authority to the Project Manager but requires assurance that the project remains within agreed tolerances. When a Project Manager identifies a potential deviation that exceeds a pre-defined tolerance, they must escalate this to the Project Board. The Project Board then needs to decide on the appropriate course of action. This might involve approving a revised plan, authorizing additional resources, or accepting the deviation if it falls within the Board’s own tolerance levels. The critical element is the Project Manager’s responsibility to report deviations, and the Project Board’s responsibility to manage exceptions that impact their level of authority or risk appetite. Therefore, the Project Board must be prepared to review and approve revised plans or provide additional resources when tolerances are forecast to be exceeded, as this is the core mechanism of managing by exception at the Project Board level.
Incorrect
The question assesses understanding of PRINCE2’s emphasis on the ‘managing by exception’ principle and its implications for the Project Board’s oversight. The Project Board delegates authority to the Project Manager but requires assurance that the project remains within agreed tolerances. When a Project Manager identifies a potential deviation that exceeds a pre-defined tolerance, they must escalate this to the Project Board. The Project Board then needs to decide on the appropriate course of action. This might involve approving a revised plan, authorizing additional resources, or accepting the deviation if it falls within the Board’s own tolerance levels. The critical element is the Project Manager’s responsibility to report deviations, and the Project Board’s responsibility to manage exceptions that impact their level of authority or risk appetite. Therefore, the Project Board must be prepared to review and approve revised plans or provide additional resources when tolerances are forecast to be exceeded, as this is the core mechanism of managing by exception at the Project Board level.